St Mary Chapel & Learning Resource Center

The new Chapel will be used by the parish school and for religious education. The Learning Resource Center will include a library, technology resources, and small group study rooms for the school and parish. In addition, the remodel will include interior upgrades including new windows. Total SF is 9,130.

September 2022 Update – During the month of September, the structural steel, flat roof decking, exterior and interior framing were installed, roof trusses were set in place and the building was sheathed. Next month electrical and mechanical rough-ins will be underway and the roofing materials will be installed.

August 2022 Update – This month underground plumbing and electrical were completed, and concrete slabs were placed for the addition and interior infills. Steel was delivered to site and exterior framing started. During September framing and steel structure will continue and the roof trusses will be set.

July 2022 Update – Construction continues the building addition. Footings and foundation walls were placed and backfilled in July. Demolition work continued interior of the existing building preparing for underground plumbing for the new bathrooms. In the next month the underground rough-ins will be installed, the building slab will be placed, and structure will begin to go vertical.

June 2022 Update – Construction began on Wednesday, June 1, following the conclusion of the school year. An addition of roughly 7,500 sq. ft., adds a new chapel, media center, and main entry. The 2,000 sq. ft. of remodeled space will include bathrooms, storage rooms, a classroom, and offices. Work started with removal of the trees along the future South wall of the new chapel. The topsoil was moved, and the foundations were excavated to prepare for the concrete building foundations. Demolition has started on the interior of the building as well. The new building plans to be open the summer of 2023.

St. Joseph Catholic School & St. Mary Academy Building Project Updates